– Project: Sedibeng Water progress projects in Maluti-a-Phofung
– Type of structure: Water project
– Capacity: 2000 water tanks

Scope: Provide water tanks to solve the water crisis in Sedibeng; Rehabilitate and equip boreholes for the harvesting of groundwater; the rehabilitation and maintenance of the current water infrastructure.

Project Overview

The department of Water and Sanitation have requested that the water crisis in Sedibeng be resolved by fixing and equipping the boreholes for harvesting groundwater and finally rehabilitating and maintaining the current water infrastructure.

Sedibeng Water has commissioned contractors to provide the area with services in relation to drought relief. The project requires contractors to install water tanks and boreholes for the area. This will improve the standard of living in the area based on the quality of service.